The development

What happened

Axios’ 20 October report describes Goldman Sachs’ warning that electricity infrastructure may limit AI expansion. The bank’s outlook concerns both financing and physical delivery, not a claim that projected data centers are already operating.

Key facts

  • Goldman forecasts global data-center power demand rising 170% from 2025 to 2030, with over 60% of that growth in the U.S.

  • Its roughly $7.6 trillion capital-spending estimate covers compute, data centers and power over 2026–2031, not annual spending.

  • About 2,600 GW of proposed U.S. generation and storage awaits grid connections. Many projects may never be built; median application-to-operation time is roughly five years.

  • Goldman projects $420 billion of global hyperscaler debt issuance in 2027. This is a forecast, not completed borrowing.

The context

Why it matters

Power delivery, permitting and construction can lag model development by years, delaying returns on planned capacity. Slower deployment may also give demand time to absorb investment. Forecast uncertainty and unbuilt grid queues limit conclusions about eventual supply.